Crews Pick Up Pace to Renovate Metro StationThe Post
An update on the Navy Yard Metro station expansion.

The station renovation is a $20 million project, paid for with federal funds, with an excavation of 65 feet and installation of elevators, ticket kiosks and eight more turnstiles, bringing the total to 13.

After falling behind in August, the pace has put it back on schedule:

Work on the station started 13 months ago and initially moved slowly. City construction permits were delayed, and in August the project was two months behind schedule, said Mamoud Hosseini, president of Clark Civil, a division of Clark Construction. Clark Civil is renovating the station while another division works on the building overhead and another builds the ballpark.

Now, Hosseini said, the station renovation is back on schedule, with all of the inside work to be finished by the end of this month. Work is also proceeding at street level, where the kiosk, ticket machines and turnstiles are to be installed.